TAHK Projects has constructed a wide range of facility projects. Below are some featured projects to illustrate our capabilities.
Home
Gas Plant Project
At TAHK Projects, numerous gas facilities have been successfully completed under our expertise.
Construction of a 300MM SCFD sweet natural gas processing plant
Cut and cap approximately 2500 piles
Fabrication and installation of piping and structural steel
Location: Grande Prairie, Ab
Terminal Project
At TAHK Projects, we are proud to have completed a significant interconnection campaign across several oil terminals
Upgrading an operating oil terminal to include new inlet lines and metering runs
Bolted and welded tie-ins completed over 19 system outages
Supply, fabrication and installation of structural steel and piping
Location: Edmonton, Ab
Truck to Rail Loading Facility
Product is trucked in from regional wells and is offloaded to the bulk storage tanks via the truck offloading rack. Railcars are shuttled to the loading rack where an automated system routes and meters product into multiple railcars simultaneously.
Module fabrication and assembly
Structural Steel installation
Set and install equipment and associated pipin
Location: Lashburn, Sk
Terminal Project
At TAHK Projects, we are proud to have completed a significant interconnection campaign across several oil terminals
Upgrading an operating oil terminal to include new inlet lines and metering runs
Bolted and welded tie-ins completed over 19 system outages
Supply, fabrication and installation of structural steel and piping
Location: edmonton, Ab
Truck to Rail Loading Facility
Module fabrication and assembly
Structural Steel installation
Set and install equipment and associated pipin
Location: Lashburn, sk
Hydrogenation-Derived Renewable Diesel Facility
Fabrication & assembly of 25 piperack modules
Fabrication & installation of 330T of structural steel
Installation of 8500 LM of piping
Location: Prince George, bc
Gas Plant
Offsite fabrication and assembly of eight piperack modules, three inlet skids, 500 tonnes of structural steel, 80,000 inches of pipe welding
Engaged in early development and planning with Client, Engineering Firm and Site Supervision Team
Onsite assembly included Inlet Compressors, Amine & Stabilization unit, Tank Farm and Power Generation Units
Location: Grand Prairie, ab
Gas Plant
Offsite fabrication and assembly of eight piperack modules, three inlet skids, 500 tonnes of structural steel, 80,000 inches of pipe welding
Engaged in early development and planning with Client, Engineering Firm and Site Supervision Team
Onsite assembly included Inlet Compressors, Amine & Stabilization unit, Tank Farm and Power Generation Units
Location: Grande Prairie, ab
Pump Station
Fabrication & installation of structural steel, piperack modules and associated piping
Installation of pre-fabricated equipment modules
Tie-in pump station to existing pipelines
Location: Grande Prairie, Ab
Compressor Station
Pre-planning and constructability from an early stage
Structural steel and pipe fabrication and installation
Installation of equipment and compressor package
Location: Edmonton, Ab
Compressor Station
Pre-planning and constructability from an early stage
Structural steel and pipe fabrication and installation
Installation of equipment and compressor package
Location: edmonton, Ab